CURRENT STATUS

Progress at major work fronts:-

The Project has achieved a cumulative progess of 98.59% till date.

Infrastructure Works Completed
Tunneling Works Completed
Diversion Cum Spillway Tunnel (DT) and Second Spillway Tunnel

Works enabling commissioning have been completed. Non-Critical works such as ST-1 & St-2 outfall works are in progress.

CFRD and Chute Spillway

Completed

Cut - off Wall Completed
Power Intake

Completed

Desilting chambers and other Right Bank Tunnels

Completed

Head race Tunnel

Completed

Surge Shaft

Completed

Pressure Shafts Left pressure Shaft- completed in all aspects.
Right pressure Shaft- Final Cleaning & inspection works in progress
Power House Civil Works

Completed

E&M Works

Unit 1, 2, 3 wet testing completed.
Unit 4, 5, 6 have been boxed up.
GIS erection works have been completed.
Pothead yard erection works have completed.